Here’s The Latest Update On Belknap Construction
Anyone in Superior knows what a huge project this Belknap Street reconstruction has become. Despite the wet weather last week, progress is rolling along. Since the last update, they've completed the sewer main to Baxter Avenue, the water main to Lamborn Avenue, and even paved asphalt in the area near Burger King, UWS, and Pilgrim Church.
There's another contractor's public meeting that will be held on June 18th at 1pm at the Superior Better Improvement Business Disctrict's office. (823 Belknap Street Suite L-10).
The next work that is expected to be completed is continuing with water & sewer main hook ups. They'll also be updating the signs along UWS, and begin paving concrete in the following areas:
Clough to Lamborn Ave
Lamborn Ave South
Grand Ave South
For more information on the project, visit the WisDOT site.