Belknap is in the early stages of a huge overhaul, which is anticipated to take place all the way until November of this year.   The latest weekly update shows that we can expect to see some storm sewer work beginning next week.

Work continues on Belknap between Banks Ave and John Ave on the west end, with bidirectional traffic on the north side of the street.  This will switch to the south side in the middle of June.

Work began earlier this week on the stretch from Birch to Hill on the East side.  Traffic has been traveling bidirectional on the north side of the street.  This will switch over the other side of Belknap in middle of July.

Progress:  The last week crews finished removing blacktop from Banks to Ogden.  This next week they will begin construction on the Hill Avenue Storm Water Basin.